Today ‹ Prev Next ›
Planned Weld Meters
1,708.1 m
4,720 pcs planned
Actual Weld Meters
1,087.0 m
63.6%
Total Downtime
933 min
Rejects: 0 pcs
Actual Qty
2,974
63% by pieces

Plan vs Actual Weld Meters by Robot

OEE by Robot

Production Detail

RobotShiftPart Plan (m)Actual (m)Achievement Qty PlanQty Actual RejectsDT (min)DT CategoryReason
Robot 1 Day Shift Seat Belt Bkt 60.0 33.6 55% 1,500 840
Robot 1 Day Shift KSRTC 2st Br Patti 72.0 72.0 100% 160 160
Robot 1 Night Shift Seat Belt Bkt 30.0 18.0 60% 750 450
Robot 1 Night Shift KSRTC 2st Br Patti 67.5 57.6 85.1% 150 128
Robot 3 Day Shift PB Bkt Front 91.0 68.9 74.7% 140 106
Robot 3 Day Shift PB Bkt Rear 62.5 54.0 87.1% 250 216
Robot 3 Night Shift PB Bkt Front 78.0 70.2 89.7% 120 108
Robot 3 Night Shift PB Bkt Rear 30.0 27.0 90% 120 108
Robot 4 Day Shift KSRTC 3st Br Patti 39.6 0.0 0% 60 0 180 Operator Not Available Fix maintenance & operator Not Available
Robot 4 Day Shift Pb leg LH 65.0 13.0 20% 100 20
Robot 4 Night Shift Pb leg LH 97.5 18.2 18.6% 150 28
Robot 5 Day Shift GSRTC Lh Leg 3x2 79.2 58.1 73.4% 120 88
Robot 5 Day Shift PB Bkt Front 78.0 71.5 91% 120 110
Robot 5 Night Shift GSRTC Lh Leg 3x2 92.4 0.0 0% 140 0 633 Other Operator SHIFT to the robot no 3
Robot 6 Day Shift GSRTC Rh Leg 2x2 79.2 59.4 74.7% 120 90
Robot 6 Day Shift GSRTC Rh leg 3x2 79.2 59.4 74.7% 120 90
Robot 6 Night Shift GSRTC Rh Leg 2x2 66.0 39.6 59.1% 100 60
Robot 6 Night Shift GSRTC Rh leg 3x2 66.0 39.6 59.1% 100 60
Robot 7 Day Shift Tnstc Leg Lh 40.0 50.0 125% 80 100 120 Other Fixture setting & program setting
Robot 7 Day Shift PB SB Assly 64.0 16.0 25% 40 10
Robot 7 Night Shift PB SB Assly 96.0 38.4 39.6% 60 24
Robot 8 Day Shift Slim 2s Seatbase TC 62.5 56.3 90.3% 50 45
Robot 8 Day Shift Slim 2st Back 62.5 56.3 90.3% 50 45
Robot 8 Night Shift Slim 2s Seatbase TC 75.0 55.0 73.3% 60 44
Robot 8 Night Shift Slim 2st Back 75.0 55.0 73.3% 60 44
TOTAL 1,708.1 1,087.0 63.6% 4,720 2,974 933

Part-wise Breakdown

PartJob CodePlan QtyActual QtyAchievementWeld Meters (m)
Seat Belt Bkt JOB-013 2,250 1,290 57.3% 51.6
PB Bkt Front JOB-010 380 324 85.3% 210.6
PB Bkt Rear JOB-011 370 324 87.6% 81.0
KSRTC 2st Br Patti JOB-004 310 288 92.9% 129.6
GSRTC Rh leg 3x2 220 150 68.2% 99.0
GSRTC Rh Leg 2x2 JOB-003 220 150 68.2% 99.0
Tnstc Leg Lh JOB-019 80 100 125% 50.0
Slim 2st Back JOB-015 110 89 80.9% 111.3
Slim 2s Seatbase TC JOB-001 110 89 80.9% 111.3
GSRTC Lh Leg 3x2 260 88 33.8% 58.1
Pb leg LH 250 48 19.2% 31.2
PB SB Assly JOB-012 100 34 34% 54.4
KSRTC 3st Br Patti JOB-005 60 0 0% 0.0

OEE Summary by Robot

Performance uses plan/actual if no cycle time set in Parts master
RobotPlanned (min)Run Time (min) AvailabilityPerformanceQualityOEE Actual QtyRejects
Robot 1 1,266 1,266 100% 100% 100% 100% 1,578
Robot 2 No Plan 0% 0% 0% 0%
Robot 3 1,266 1,266 100% 87.1% 100% 87.1% 538
Robot 4 1,266 1,086 85.8% 17.3% 100% 14.8% 48
Robot 5 1,266 633 50% 100% 100% 50% 198
Robot 6 1,266 1,266 100% 79% 100% 79% 300
Robot 7 1,266 1,146 90.5% 61.2% 100% 55.4% 134
Robot 8 1,266 1,266 100% 81.8% 100% 81.8% 178

OEE at a Glance — Dept. Average

7 robots with data
78.3% Availability
65.8% Performance
87.5% Quality
58.5% OEE

Robot Arc / Movement Time

From robot counter
RobotArc Time (min)Movement Time (min)Notes
Robot 1
Robot 3
Robot 4
Robot 5
Robot 6
Robot 7
Robot 8