Today ‹ Prev Next ›
Planned Weld Meters
1,298.4 m
4,654 pcs planned
Actual Weld Meters
878.0 m
67.6%
Total Downtime
540 min
Rejects: 0 pcs
Actual Qty
4,336
93.2% by pieces

Plan vs Actual Weld Meters by Robot

OEE by Robot

Production Detail

RobotShiftPart Plan (m)Actual (m)Achievement Qty PlanQty Actual RejectsDT (min)DT CategoryReason
Robot 1 Day Shift Seat Belt Bkt 60.0 60.0 100% 1,500 1,500
Robot 1 Day Shift KSRTC 2st Br Patti 54.0 0% 120 0
Robot 1 Night Shift Seat Belt Bkt 48.0 65.6 135.4% 1,200 1,640 60 Other Run shift
Robot 1 Night Shift KSRTC 2st Br Patti 63.0 18.0 28.6% 140 40
Robot 2 Day Shift Slim Leg Lh 83.6 57.0 68.7% 220 150
Robot 3 Day Shift Tnstc 2St Sb Frame 55.0 44.0 80% 50 40
Robot 3 Day Shift PB Bkt Front 97.5 93.6 95.9% 150 144
Robot 3 Night Shift PB Bkt Front 97.5 65.0 67% 150 100 180 Other Operator Shift to robot no 4
Robot 4 Day Shift Pb leg LH 52.0 49.4 94.2% 80 76 120 Changeover Ksrtc 3 st br setting
Robot 4 Night Shift KSRTC 3st Br Patti 95.0 27.7 28.4% 144 42
Robot 4 Night Shift Pb leg LH 39.0 31.2 79.5% 60 48
Robot 5 Day Shift GSRTC Rh leg 3x2 79.2 62.0 78.5% 120 94
Robot 5 Day Shift PB Bkt Front 39.0 32.5 82.1% 60 50
Robot 5 Night Shift GSRTC Lh Leg 3x2 118.8 85.8 72% 180 130
Robot 6 Day Shift GSRTC Rh Leg 2x2 79.2 26.4 32.9% 120 40 120 Quality Issue Fixture toggle setting & program setting
Robot 6 Day Shift GSRTC Rh leg 3x2 79.2 48.8 60.8% 120 74
Robot 6 Night Shift GSRTC Rh Leg 2x2 79.2 48.8 60.8% 120 74 60 Quality Issue Cross tube Gap fitting problem
Robot 6 Night Shift GSRTC Rh leg 3x2 79.2 62.0 78.5% 120 94
TOTAL 1,298.4 878.0 67.6% 4,654 4,336 540

Part-wise Breakdown

PartJob CodePlan QtyActual QtyAchievementWeld Meters (m)
Seat Belt Bkt JOB-013 2,700 3,140 116.3% 125.6
PB Bkt Front JOB-010 360 294 81.7% 191.1
GSRTC Rh leg 3x2 360 262 72.8% 172.9
Slim Leg Lh JOB-016 220 150 68.2% 57.0
GSRTC Lh Leg 3x2 180 130 72.2% 85.8
Pb leg LH 140 124 88.6% 80.6
GSRTC Rh Leg 2x2 JOB-003 240 114 47.5% 75.2
KSRTC 3st Br Patti JOB-005 144 42 29.2% 27.7
KSRTC 2st Br Patti JOB-004 260 40 15.4% 18.0
Tnstc 2St Sb Frame 50 40 80% 44.0

OEE Summary by Robot

Performance uses plan/actual if no cycle time set in Parts master
RobotPlanned (min)Run Time (min) AvailabilityPerformanceQualityOEE Actual QtyRejects
Robot 1 1,266 1,206 95.3% 92.8% 100% 88.4% 3,180
Robot 2 633 633 100% 67.1% 100% 67.1% 150
Robot 3 1,266 1,086 85.8% 100% 100% 85.8% 284
Robot 4 1,266 1,146 90.5% 54% 100% 48.9% 166
Robot 5 1,266 1,266 100% 71.7% 100% 71.7% 274
Robot 6 1,266 1,086 85.8% 86.6% 100% 74.2% 282
Robot 7 No Plan 0% 0% 0% 0%
Robot 8 No Plan 0% 0% 0% 0%

OEE at a Glance — Dept. Average

6 robots with data
69.7% Availability
59.0% Performance
75.0% Quality
54.5% OEE

Robot Arc / Movement Time

From robot counter
RobotArc Time (min)Movement Time (min)Notes
Robot 1 234.2 min 1,133.3 min
Robot 2 281.1 min 598.7 min
Robot 3 154.0 min 778.2 min
Robot 4 185.2 min 1,055.9 min
Robot 5 184.8 min 1,055.9 min
Robot 6 252.4 min 810.2 min