Daily Production Report
Thursday, 05-Mar-2026
Planned Weld Meters
1,013.3 m
4,400 pcs planned
Actual Weld Meters
681.6 m
67.2%
Total Downtime
783 min
Rejects: 0 pcs
Actual Qty
3,721
84.6% by pieces
Plan vs Actual Weld Meters by Robot
OEE by Robot
Production Detail
| Robot | Shift | Part | Plan (m) | Actual (m) | Achievement | Qty Plan | Qty Actual | Rejects | DT (min) | DT Category | Reason |
|---|---|---|---|---|---|---|---|---|---|---|---|
| Robot 1 | Day Shift | Seat Belt Bkt | 48.0 | 45.9 | 93.8% | 1,200 | 1,148 | — | — | — | — |
| Robot 1 | Day Shift | KSRTC 2st Br Patti | 45.0 | 54.0 | 120% | 100 | 120 | — | — | — | — |
| Robot 1 | Night Shift | Seat Belt Bkt | 60.0 | 59.0 | 98.3% | 1,500 | 1,476 | — | — | — | — |
| Robot 1 | Night Shift | KSRTC 2st Br Patti | 67.5 | 58.5 | 86.6% | 150 | 130 | — | — | — | — |
| Robot 2 | Day Shift | Slim Leg Lh | 83.6 | 64.6 | 77.1% | 220 | 170 | — | 30 | No Material | Bending tube short |
| Robot 2 | Night Shift | Slim Leg Lh | 83.6 | 0.0 | 0% | 220 | 0 | — | 633 | Operator Not Available | Operator Not Available |
| Robot 3 | Day Shift | PB Bkt Front | 97.5 | 94.3 | 96.9% | 150 | 145 | — | — | — | — |
| Robot 3 | Day Shift | PB Bkt Rear | 37.5 | 36.3 | 97.3% | 150 | 145 | — | — | — | — |
| Robot 3 | Night Shift | Tnstc 2St Sb Frame | 55.0 | 34.1 | 61.8% | 50 | 31 | — | 60 | Other | Material setting |
| Robot 5 | Day Shift | GSRTC Lh Leg 2x2 | 99.0 | 85.8 | 85.9% | 150 | 130 | — | — | — | — |
| Robot 5 | Night Shift | GSRTC Lh Leg 3x2 | 99.0 | 59.4 | 59.6% | 150 | 90 | — | — | — | — |
| Robot 6 | Day Shift | GSRTC Rh Leg 2x2 | 52.8 | 44.9 | 84.6% | 80 | 68 | — | 60 | Operator Not Available | — |
| Robot 6 | Day Shift | GSRTC Rh leg 3x2 | 52.8 | 44.9 | 84.6% | 80 | 68 | — | — | — | — |
| Robot 6 | Night Shift | GSRTC Rh Leg 2x2 | 66.0 | 0.0 | 0% | 100 | 0 | — | — | — | — |
| Robot 6 | Night Shift | GSRTC Rh leg 3x2 | 66.0 | — | 0% | 100 | 0 | — | — | — | — |
| TOTAL | 1,013.3 | 681.6 | 67.2% | 4,400 | 3,721 | — | 783 | ||||
Part-wise Breakdown
| Part | Job Code | Plan Qty | Actual Qty | Achievement | Weld Meters (m) |
|---|---|---|---|---|---|
| Seat Belt Bkt | JOB-013 | 2,700 | 2,624 | 97.2% | 105.0 |
| KSRTC 2st Br Patti | JOB-004 | 250 | 250 | 100% | 112.5 |
| Slim Leg Lh | JOB-016 | 440 | 170 | 38.6% | 64.6 |
| PB Bkt Rear | JOB-011 | 150 | 145 | 96.7% | 36.3 |
| PB Bkt Front | JOB-010 | 150 | 145 | 96.7% | 94.3 |
| GSRTC Lh Leg 2x2 | JOB-002 | 150 | 130 | 86.7% | 85.8 |
| GSRTC Lh Leg 3x2 | — | 150 | 90 | 60% | 59.4 |
| GSRTC Rh Leg 2x2 | JOB-003 | 180 | 68 | 37.8% | 44.9 |
| GSRTC Rh leg 3x2 | — | 180 | 68 | 37.8% | 44.9 |
| Tnstc 2St Sb Frame | — | 50 | 31 | 62% | 34.1 |
OEE Summary by Robot
Performance uses plan/actual if no cycle time set in Parts master| Robot | Planned (min) | Run Time (min) | Availability | Performance | Quality | OEE | Actual Qty | Rejects |
|---|---|---|---|---|---|---|---|---|
| Robot 1 | 1,266 | 1,266 | 100% | 100% | 100% | 100% | 2,874 | — |
| Robot 2 | 1,266 | 603 | 47.6% | 79.9% | 100% | 38% | 170 | — |
| Robot 3 | 1,266 | 1,206 | 95.3% | 74.7% | 100% | 71.1% | 321 | — |
| Robot 4 No Plan | — | — | 0% | 0% | 0% | 0% | — | — |
| Robot 5 | 1,266 | 1,266 | 100% | 57.9% | 100% | 57.9% | 220 | — |
| Robot 6 | 1,266 | 1,206 | 95.3% | 37.6% | 100% | 35.8% | 136 | — |
| Robot 7 No Plan | — | — | 0% | 0% | 0% | 0% | — | — |
| Robot 8 No Plan | — | — | 0% | 0% | 0% | 0% | — | — |
OEE at a Glance — Dept. Average
5 robots with dataRobot Arc / Movement Time
From robot counter| Robot | Arc Time (min) | Movement Time (min) | Notes |
|---|---|---|---|
| Robot 1 | 136.0 min | 624.4 min | — |
| Robot 3 | 212.7 min | 653.4 min | — |
| Robot 5 | 99.2 min | 633.3 min | — |
| Robot 6 | 108.2 min | 483.2 min | — |