Daily Production Report
Wednesday, 04-Mar-2026
Planned Weld Meters
757.4 m
4,590 pcs planned
Actual Weld Meters
303.9 m
40%
Total Downtime
1091 min
Rejects: 0 pcs
Actual Qty
2,982
65% by pieces
Plan vs Actual Weld Meters by Robot
OEE by Robot
Production Detail
| Robot | Shift | Part | Plan (m) | Actual (m) | Achievement | Qty Plan | Qty Actual | Rejects | DT (min) | DT Category | Reason |
|---|---|---|---|---|---|---|---|---|---|---|---|
| Robot 1 | Day Shift | Seat Belt Bkt | 60.0 | 41.0 | 68.3% | 1,500 | 1,025 | — | 158 | Operator Not Available | Operator Not Available |
| Robot 1 | Night Shift | Seat Belt Bkt | 78.0 | 60.7 | 76.9% | 1,950 | 1,517 | — | — | — | — |
| Robot 2 | Night Shift | Slim Leg Lh | 0.0 | — | 0% | 0 | 0 | — | 633 | Operator Not Available | No operator Available |
| Robot 3 | Day Shift | PB Bkt Front | 97.5 | 91.0 | 93.8% | 150 | 140 | — | — | — | — |
| Robot 3 | Day Shift | PB Bkt Rear | 37.5 | 35.0 | 94.6% | 150 | 140 | — | — | — | — |
| Robot 3 | Night Shift | PB Bkt Front | 65.0 | 45.5 | 69.2% | 100 | 70 | — | — | — | — |
| Robot 3 | Night Shift | PB Bkt Rear | 25.0 | 17.5 | 68% | 100 | 70 | — | — | — | — |
| Robot 5 | Day Shift | GSRTC Lh Leg 2x2 | 52.8 | — | 0% | 80 | 0 | — | — | — | — |
| Robot 5 | Night Shift | GSRTC Lh Leg 2x2 | 66.0 | 13.2 | 19.7% | 100 | 20 | — | 300 | No Material | Operator Not Available |
| Robot 6 | Day Shift | Slim Leg Lh | 38.0 | — | 0% | 100 | 0 | — | — | — | — |
| Robot 6 | Day Shift | GSRTC Rh Leg 2x2 | 52.8 | — | 0% | 80 | 0 | — | — | — | — |
| Robot 6 | Day Shift | GSRTC Rh leg 3x2 | 52.8 | — | 0% | 80 | 0 | — | — | — | — |
| Robot 6 | Night Shift | GSRTC Rh Leg 2x2 | 66.0 | — | 0% | 100 | 0 | — | — | — | — |
| Robot 6 | Night Shift | GSRTC Rh leg 3x2 | 66.0 | — | 0% | 100 | 0 | — | — | — | — |
| TOTAL | 757.4 | 303.9 | 40% | 4,590 | 2,982 | — | 1091 | ||||
Part-wise Breakdown
| Part | Job Code | Plan Qty | Actual Qty | Achievement | Weld Meters (m) |
|---|---|---|---|---|---|
| Seat Belt Bkt | JOB-013 | 3,450 | 2,542 | 73.7% | 101.7 |
| PB Bkt Front | JOB-010 | 250 | 210 | 84% | 136.5 |
| PB Bkt Rear | JOB-011 | 250 | 210 | 84% | 52.5 |
| GSRTC Lh Leg 2x2 | JOB-002 | 180 | 20 | 11.1% | 13.2 |
| GSRTC Rh Leg 2x2 | JOB-003 | 180 | 0 | 0% | — |
| GSRTC Rh leg 3x2 | — | 180 | 0 | 0% | — |
| Slim Leg Lh | JOB-016 | 100 | 0 | 0% | — |
OEE Summary by Robot
Performance uses plan/actual if no cycle time set in Parts master| Robot | Planned (min) | Run Time (min) | Availability | Performance | Quality | OEE | Actual Qty | Rejects |
|---|---|---|---|---|---|---|---|---|
| Robot 1 | 1,266 | 1,108 | 87.5% | 72.7% | 100% | 63.6% | 2,542 | — |
| Robot 2 | 633 | 0 | 0% | 0% | 100% | 0% | 0 | — |
| Robot 3 | 1,266 | 1,266 | 100% | 74.6% | 100% | 74.6% | 420 | — |
| Robot 4 No Plan | — | — | 0% | 0% | 0% | 0% | — | — |
| Robot 5 | 1,266 | 966 | 76.3% | 6.9% | 100% | 5.3% | 20 | — |
| Robot 6 | 1,266 | 1,266 | 100% | 0% | 100% | 0% | 0 | — |
| Robot 7 No Plan | — | — | 0% | 0% | 0% | 0% | — | — |
| Robot 8 No Plan | — | — | 0% | 0% | 0% | 0% | — | — |
OEE at a Glance — Dept. Average
3 robots with dataRobot Arc / Movement Time
From robot counter| Robot | Arc Time (min) | Movement Time (min) | Notes |
|---|---|---|---|
| Robot 1 | 185.1 min | 1,084.7 min | — |
| Robot 3 | 280.3 min | 1,000,000.0 min | — |
| Robot 4 | 1.0 min | 3.5 min | — |
| Robot 5 | 87.6 min | 567.8 min | — |