Planned Weld Meters
1,074.3 m
4,580 pcs planned
Actual Weld Meters
714.4 m
66.5%
Total Downtime
410 min
Rejects: 0 pcs
Actual Qty
3,399
74.2% by pieces

Plan vs Actual Weld Meters by Robot

OEE by Robot

Production Detail

RobotShiftPart Plan (m)Actual (m)Achievement Qty PlanQty Actual RejectsDT (min)DT CategoryReason
Robot 1 Day Shift Seat Belt Bkt 40.0 27.9 67.5% 1,000 697 120 Machine Breakdown Wire feeder Roller problem
Robot 1 Night Shift Seat Belt Bkt 72.0 59.0 81.9% 1,800 1,475
Robot 2 Day Shift Slim Leg Lh 95.0 68.4 71.6% 250 180 20 No Material Leg bending not available
Robot 2 Night Shift Slim Leg Lh 76.0 45.6 59.2% 200 120 120 No Material Cutting tube short
Robot 3 Day Shift PB Bkt Front 97.5 93.6 95.9% 150 144
Robot 3 Day Shift PB Bkt Rear 37.5 36.0 97.3% 150 144
Robot 3 Night Shift PB Bkt Rear 30.0 32.0 106.7% 120 128
Robot 3 Night Shift PB Bkt Front 97.5 83.2 85.6% 150 128
Robot 4 Day Shift Slim Leg Lh 19.0 11.4 57.9% 50 30 120 No Material Cutting tube short
Robot 4 Day Shift Slim Leg Rh 19.0 11.4 57.9% 50 30
Robot 5 Day Shift GSRTC Lh Leg 2x2 66.0 52.8 78.8% 100 80 30 Changeover Fix changes
Robot 5 Night Shift PB Bkt Front 78.0 13.0 16.7% 120 20
Robot 5 Night Shift GSRTC Lh Leg 2x2 79.2 71.3 89.9% 120 108
Robot 6 Day Shift GSRTC Rh Leg 2x2 66.0 52.8 78.8% 100 80
Robot 6 Night Shift GSRTC Rh Leg 2x2 105.6 0.0 0% 160 0
Robot 7 Day Shift PB SB Assly 96.0 56.0 58.3% 60 35
TOTAL 1,074.3 714.4 66.5% 4,580 3,399 410

Part-wise Breakdown

PartJob CodePlan QtyActual QtyAchievementWeld Meters (m)
Seat Belt Bkt JOB-013 2,800 2,172 77.6% 86.9
Slim Leg Lh JOB-016 500 330 66% 125.4
PB Bkt Front JOB-010 420 292 69.5% 189.8
PB Bkt Rear JOB-011 270 272 100.7% 68.0
GSRTC Lh Leg 2x2 JOB-002 220 188 85.5% 124.1
GSRTC Rh Leg 2x2 JOB-003 260 80 30.8% 52.8
PB SB Assly JOB-012 60 35 58.3% 56.0
Slim Leg Rh JOB-018 50 30 60% 11.4

OEE Summary by Robot

Performance uses plan/actual if no cycle time set in Parts master
RobotPlanned (min)Run Time (min) AvailabilityPerformanceQualityOEE Actual QtyRejects
Robot 1 1,266 1,146 90.5% 60% 99.6% 54.1% 2,172 8
Robot 2 1,266 1,126 88.9% 75.5% 96.7% 64.9% 300 10
Robot 3 1,266 1,266 100% 96.7% 99.1% 95.8% 544 5
Robot 4 633 513 81% 33.1% 96.7% 26% 60 2
Robot 5 1,266 1,236 97.6% 55.9% 98.1% 53.6% 208 4
Robot 6 1,266 1,266 100% 21.1% 92.5% 19.5% 80 6
Robot 7 633 633 100% 51.1% 88.6% 45.3% 35 4
Robot 8 No Plan 0% 0% 0% 0%

OEE at a Glance — Dept. Average

7 robots with data
82.3% Availability
49.2% Performance
83.9% Quality
44.9% OEE

Quality Loss Analysis

RobotShiftPartActual ReworkRework ReasonsScrapScrap ReasonsFPY%
Robot 1 Day Shift Seat Belt Bkt 697 8 Blow hole 98.9%
Robot 2 Day Shift Slim Leg Lh 180 10 Run shift 94.4%
Robot 3 Day Shift PB Bkt Front 144 5 Front bkt weld shift 96.5%
Robot 4 Day Shift Slim Leg Lh 30 2 Tube undersize 93.3%
Robot 5 Day Shift GSRTC Lh Leg 2x2 80 4 Cross tube Gap 95%
Robot 6 Day Shift GSRTC Rh Leg 2x2 80 6 Cross tube Gap 92.5%
Robot 7 Day Shift PB SB Assly 35 4 Bkt over size 88.6%